CONSTRUCTION UPDATES – 22nd May 2026
Works on site continue to progress across multiple areas of the basement structure. Concrete pours are underway to the south-east slab and south-west footings, with the south-west slab also prepared for its next pour sequence. Shotcrete activities remain ongoing across the northern and western retaining walls, including the central capping beam and wall sections. Bulk excavation to the north-west continues to advance, alongside preparations for the loading bay and the commencement of in-ground basement tank works.